Cat Bi International Airport

Innovative runway pavement design using 40/50 bitumen and PMB.
This the first Airport project in Vietnam under the investment of province (Hai Phong City) instead of invested by ACV as other projects. The project owner - Hai Phong Bridge Project Unit - required high quality of asphalt material to ensure the long time service life of the runway with increasing of number and load of airplane. The KBC Naphthenic 40/50 bitumen had been use to make hard asphalt layer with full supplied of 4500mt by ADCo. This is the first Runway project to applied the 40/50 for the asphalt base. The runway remains good quality till this moment over year of operations.
 
Project name: Cat Bi International Airport
Year: 2014-2015
Location: Hai Phong City
Investors: Hai Phong City
Contractors: ACC, Phuc Loc
Consultant: ADCC
Volume: 4,500 MT KBC 40/50 & 1,200 MT PMB III
Scope of project: 3.4km of runway
Spec. of Products: 40/50 & PMB III

Other Projects

Maybe you are interested in our other signature projects

Ha Noi Formula 1 Racetrack

Ha Noi Formula 1 Racetrack

A showcase of innovation and expertise for the first-ever Formula 1 racetrack in Vietnam. Ha Noi Formula 1 Racetrack (North Vietnam) - total length of 5.6 km, includes 23 turns, with a unique hybrid design, combining a street circuit's characteristic with a permanent track layout to reach a top speed of 335 km/h for F1 car drivers; first ever in the history of Vietnam and the circuit itself. The designing and paving works of high-standard racetrack pavement were done under the supervision of a German F1 accredited consultant. ADCo was awarded for the supply of a complete range of bituminous binder for Ha Noi F1 Race track including:   More than 1,500 MT polymer-modified bitumen for wearing and binder course following MSCR PG specification More than 800 MT Naphthenic based Bitumen from KBC (the Group refinery in Malaysia) for Base course Polymer Modified Emulsion for Tack coat ADCo Trackless System - A first in Viet Nam was implemented and sprayed by ADCo to preserve the integrity of the tack coat and ensure cleanliness of the site ADCo Anti-sticking agent (ASC) from the Group was part of the package for asphalt paving application.   Project name: Ha Noi Formula 1 Racetrack Products: PMB III, 60/70 Bitumen, CRS-1P Year: 2019 - 2020 Location: Ha Noi Investors: VINGROUP - Ha noi City Contractors: Minh Tam Consultant: Tilke - Germany Construction section:  2 layer of PMB III F1 including binder and wearing course on existing road 3 layers of asphalt including 60/70 KBC base course & PMB III F1 binder and wearing course for new construction