Cat Bi International Airport
Innovative runway pavement design using 40/50 bitumen and PMB.
This the first Airport project in Vietnam under the investment of province (Hai Phong City) instead of invested by ACV as other projects. The project owner - Hai Phong Bridge Project Unit - required high quality of asphalt material to ensure the long time service life of the runway with increasing of number and load of airplane. The KBC Naphthenic 40/50 bitumen had been use to make hard asphalt layer with full supplied of 4500mt by ADCo. This is the first Runway project to applied the 40/50 for the asphalt base. The runway remains good quality till this moment over year of operations.
Project name: Cat Bi International Airport
Year: 2014-2015
Location: Hai Phong City
Investors: Hai Phong City
Contractors: ACC, Phuc Loc
Consultant: ADCC
Volume: 4,500 MT KBC 40/50 & 1,200 MT PMB III
Scope of project: 3.4km of runway
Spec. of Products: 40/50 & PMB III